Name: 
 

Unit06-01-EST



Multiple Choice
Identify the choice that best completes the statement or answers the question.
 

 1. 

Which table below, would best match the EST graph shown at the right?


mc001-1.jpg

 


a.

mc001-2.jpg

 


b.

mc001-3.jpg

 


c.
mc001-4.jpg
 

 2. 

In the following Earliest Start Time (ESP) graph, assume each unit of time is an hour.
mc002-1.jpg


In the EST graph, two tasks are required before starting task E.  Which prerequisite task finishes first?

 

a.
C
c.
G
b.
D
d.
F
 

 3. 

In the following Earliest Start Time (EST) graph, assume each unit of time is an hour.
mc003-1.jpg

In the EST graph, how long does it take to do just task E?


a.
4
c.
8
b.
6
d.
14
 

 4. 

Using the following EST graph to answer the question (assuming the time unit is days).

mc004-1.jpg

Which of the following is the correct critical path?

 

a.
BEFHIJ, 175
c.
BEGHIJ, 175
b.
ACDGHIJ, 175
d.
ABCDEFGHIJ, 175
 



 
Check Your Work     Start Over