Multiple Choice Identify the
choice that best completes the statement or answers the question.
|
|
|
1.
|
Which table below, would best match
the EST graph shown at the right?
| | | |
|
|
|
2.
|
In the following Earliest Start Time (ESP) graph, assume each unit of time is an
hour.
In the EST graph,
two tasks are required before starting task E. Which prerequisite task finishes first?
|
|
|
3.
|
In the following Earliest Start Time (EST) graph, assume each unit of time is an
hour.
In the EST graph, how
long does it take to do just task E?
|
|
|
4.
|
Using the following EST graph to answer the question (assuming the time unit is
days).
Which of the following
is the correct critical path?
a. | BEFHIJ, 175 | c. | BEGHIJ, 175 | b. | ACDGHIJ, 175 | d. | ABCDEFGHIJ, 175 |
|